DPS Engineering Division - Construction List
|
|
Road Construction Activity
|
Project Type
|
Construction Year
|
| Grosse Ile Parkway / Trenton Channel |
Bridge Rehabilitation |
2007 |
| Minor punchlist work to be scheduled November 22, 23, 2008. Temporary Closure. |
| Canton Twp., Local Road Maintenance |
Pavement Patching |
2008 |
| Punchlist |
| Howe Rd (Van Born to Michigan Ave) |
Resurface Road |
2008 |
| Punchlist. |
| Hubbard (Evergreen to M-39) |
Resurface Road |
2008 |
| Complete. |
| Lilley Road (Ford to Warren) |
Reconstruct Road |
2008 |
| Complete. |
| Lilley Road/Hanford |
Intersection Widening |
2008 |
| Minor punchlist. |
| Mack Ave (Moross to Vernier) |
Resurface Road |
2008 |
| Restoration work. |
| Mercury Drive (Hubbard to Ford Rd) |
Resurface Road |
2008 |
| Complete. |
| Northline (Fort Street to Jefferson Ave) |
Resurface Road |
2008 |
| Signs and punchlist. |
| Oakwood (Park to Michigan Ave) |
Reconstruct Road |
2008 |
| Complete |
| Piquette Building Facade Restoration |
Building Renovation |
2008 |
| Building renovation on-going. Glass replacement.
|
| Schaefer (West Jefferson to Detroit City Limit) |
Resurface Road |
2008 |
| Punchlist. |
| Sheldon Road @ CSX Rail Road |
Grade Separation |
2008 |
| Sheldon Road CLOSED south of M-14. Follow detour. Concrete paving. Train on permanent tracks. |
| Six Mile Road (Haggerty - Farmington) |
Resurface Road |
2008 |
| Punchlist. |
| Southwest Detroit Bike Path |
Resurface Road |
2008 |
| Complete. |
| Toledo Road (Northline to Moran) |
Resurface Road |
2008 |
| Punchlist. (Spring) |
| Toledo Road (Southfield to Outer Drive) |
Resurface Road |
2008 |
| Complete. |
| Traffic Signals at Evergreen (North of Hubbard) |
Traffic Signal Upgrade |
2008 |
| Foundation work complete. Wiring to start the week of 24 November. |
| Traffic Signals Upgrades @ 5 Intersections in Woodhaven |
Traffic Signal Upgrade |
2008 |
| All intersections under construction. Starting overhead and wiring. Signals at 2 of 5 intersections are in place. |
| Warren (Schaefer to Lonyo) |
Resurface Road |
2008 |
| Complete. |
| Warren @ Beck Intersection |
Intersection Widening |
2008 |
| Complete. |